Date
Steps
Key tasks
Milestone and/or deliverable
March 2012
Planning and setting-up
Online induction

Finalisation of project plan and contracts
Attend online Induction

Join online collaborative space

Submit project plan

Contracts finalised

(40% milestone payment)
March-April 2012
Trial implementation
Research and trial technology
Provide status updates to ETT PM and share with other teams
Provide verbal/online project updates
April 2012
Mid-project status report
Online meeting
Present to reference group if requested
Write mid-project report
Attend online meeting

Present to reference group if requested

Present mid-project report

(30% milestone payment)
June 2012
Reporting
Online or f2f meeting (Melbourne), present project findings, write final report by June 8, 2012
Attend online or f2f meeting

Participate in online activities

Submit final report by June 8, 2012 and any agreed trial outputs

(30% milestone payment)